over 2 years ago - AG_MarkPittam - Direct link
Hi, @NalyKalZul

I have investigated this issue and it appears that the streamline discount will only be applied once you have placed the dome blueprint on the ground.

A medium dome shown in the build menu shows the base resources needed which are 120 concrete, 50 metals and 20 polymers. After placing the blueprint for the medium dome, the resources needed are 60 concrete, 25 metals and 20 polymers, this would be seen after selecting the blueprint in the UI panel on the right.